Check out this room. Tight AF. It took all day just to take out the burner of this boiler, clean it and all other parts attached and put it all back together. The boiler requires 6" clearance on top. It has none. It needs a new gas valve and some other parts. The duct work needs to come out in order to change the valve because it needs space to swing at the top. Because the cost of parts and labour to get all this done. The customer is probably going to change the boiler out for a smaller foot print and lower it on the wall. The sub on site shook my hand and said thanks for not walking away. I was very frustrated with this one but kept my cool lol.